September 3rd, 2010
Work starts today on the North side of Main Street with curb and gutter removal.
- Phase 1: Curb and gutter removal, sub-drain installation, curb and gutter installation, some minor brick work in front of Adel TV & Appliance.
- Phase 2: Removal of the sidewalk panels and then replacement of the sidewalk.
Each phase will take about 10 working days (weather pending). Access to buildings will be maintained.