October 6th, 2010
Today crews start the removal and replacement of the sidewalk on the south side of Main Street.
The parking area will be removed first. That area will then be poured back with new concrete and matched to the existing brick street.
Then the sidewalk section next to the buildings will be removed and replaced. There will be access to the building at all times. The contractor has bridges he will use to ensure this will happen.