July 16th, 2010
It’s been a busy week for the street crews. The center lanes were poured on both Court and Main. The parking has been graveled and the curb and gutter has been poured on Main.
Today the crews are removing the old cement next to the highway in preparation of starting on the sidewalks along Main Street. The sidewalk construction will incorporate bridges so that customers can still visit their favorite downtown businesses.
DiscoverAdel will have daily information on the business affected and their alternate access points during the sidewalk stage.