Brick Street Project Updates
- July 27, 2010
Crews are working to lay the bricks on Court Street.
The bump-outs on Main are planned to be poured today. The sidewalk in front of Kinninck’s is planned for later this this afternoon or tomorrow.
- July 23, 2010
Despite early morning rains, the crews are busy getting Main St. ready for sidewalks to be poured Saturday.
Hopefully front door access to the businesses affected by the sidewalk delay will be open Monday. The affected businesses are still open during the construction, access information can be found here.
- July 22, 2010
Crews are working steadily to fill the coal chutes on Main Street. Front door access to those businesses are currently closed. Click here to view alternative access information for the affected businesses.
A reminder that there will be a Public Brick Street Project update meeting this evening at the Adel City Hall. The meeting will begin at 6:00pm. Please bring any questions or concerns you have about the project.
If you are unable to attend the meeting please contact Chad Bird at 515-993-4525 for questions or concerns.
- July 21, 2010
Crews are pouring sidewalk in front of the businesses along Main street. They are also in the progress of filling coal chutes with cement along that road.
It appears that the entire street is without front door access. Click here to find alternative access information to the affected businesses.
- July 20, 2010
In spite of the rain Monday and this morning, the crews have been busy today, pouring cement on Court St. for the parking.
They’ve also started the sidewalk replacement on Main Street. The affected businesses’ are; Iowa Title, Anytime Fitness, Russell Slater Insurance, Russell Abstract, and Jennings Law Office. The crews are working into the evening to get the sections done as quickly as possible and to minimize access issues for those businesses.
Warning: Use of undefined constant pagination - assumed 'pagination' (this will throw an Error in a future version of PHP) in /home2/adelblog/public_html/wp-content/themes/DA theme/functions.php on line 1842
Project Photo Gallery
no images were found
The following companies were contracted to provide services during the Brick Street Renovation Project
McClure Engineering Engineers Manatts General Contractor and Concrete Paving Elder Corporation Earthwork, Pipe Hardscape Solutions Brick Installation Absolute Concrete Concrete American Fence Railing Breton Enterprises Electrical Quality Striping Inc., DBA DPLM Pavement Marking Quality Traffic Control Inc. Traffic Control Lenhart Plumbing Water Fountain Rothamel Turf Farms, Inc. Landscaping Soil-Tek Silt Fence Swanson Masonry Masonry