September 3rd, 2010

Work starts today on the North side of Main Street with curb and gutter removal.

  • Phase 1: Curb and gutter removal, sub-drain installation, curb and gutter installation, some minor brick work in front of Adel TV & Appliance.
  • Phase 2: Removal of the sidewalk panels and then replacement of the sidewalk.

Each phase will take about 10 working days (weather pending). Access to buildings will be maintained.