Brick Street Project Updates

  • April 4th, 2011
  • All,

    As our crews continue to work diligently on punch list items many details are being addressed.

    The major work task this week will be to address the ‘trench” settling along the north side of Main Street in the 900 block. Work on this area should commence this week with removal of the brick, compaction and concrete work and then replacing the brick. It is anticipated this work will take the majority of the week.

    Parking on the north side of Main will be prohibited during the work on this punch list item.

    Other items in the works or recently completed include:

    All major lighting and electrical work is complete, there is still some minor hand work to complete.

    Landscaping plans are under way but must wait for the critical planting date of April 15 to actual begin. Once begun, that work should be completed in short order.

    The new street banners are up, new banners with a new look.

    All areas of the street and parking remain open. Only spot parking or driving restrictions will be enforced as work progresses.

    Street signs and parking zone painting is planned but is also weather dependant. This work should commence around the April 15th date also.

    As always, thank you for your patience.

    Chad

    Chad A. Bird
    City Administrator
    City of Adel
    515-993-4525


 

Project Photo Gallery

The following companies were contracted to provide services during the Brick Street Renovation Project

McClure Engineering Engineers

Manatts General Contractor and Concrete Paving

Elder Corporation Earthwork, Pipe

Hardscape Solutions Brick Installation

Absolute Concrete Concrete

American Fence Railing

Breton Enterprises Electrical

Quality Striping Inc., DBA DPLM Pavement Marking

Quality Traffic Control Inc. Traffic Control

Lenhart Plumbing Water Fountain

Rothamel Turf Farms, Inc. Landscaping

Soil-Tek Silt Fence

Swanson Masonry Masonry