Brick Street Project Updates

  • April 7th, 2011
  • All,

    It is time to finally paint our parking stripes in the downtown area.

    Please be aware of the following general schedule for the paint crews.

    Starting Friday morning (April 8th) crews will begin the process to paint all traffic markings. It is anticipated that they will start on Main Street but this may be dependent on the number of vehicles in the area.

    Once the process begins crews have been instructed to close no more than two parking sections (city blocks) at a time. Parking area being defined as a city block parking section – one entire side of the street. Once that area is complete and dry another area will be closed and so on.

    Painting should take about 3 days to complete. The process will include grinding a portion of the concrete away and filling the ground section with durable epoxy paint.

    After the painting is complete we will then move to permanent signage installation – perhaps by the end of next week (April 15th).

    On another note, clean up of the Courthouse lawn will be complete by Monday, April 11th. Sod work will begin after the recommended planting date of April 15th.

    As always, thank you for your patience.

    Chad

    Chad A. Bird
    City Administrator
    City of Adel
    515-993-4525

 

Project Photo Gallery

The following companies were contracted to provide services during the Brick Street Renovation Project

McClure Engineering Engineers

Manatts General Contractor and Concrete Paving

Elder Corporation Earthwork, Pipe

Hardscape Solutions Brick Installation

Absolute Concrete Concrete

American Fence Railing

Breton Enterprises Electrical

Quality Striping Inc., DBA DPLM Pavement Marking

Quality Traffic Control Inc. Traffic Control

Lenhart Plumbing Water Fountain

Rothamel Turf Farms, Inc. Landscaping

Soil-Tek Silt Fence

Swanson Masonry Masonry